Building a Pipeline

Scroll through the installation process to understand the steps of building a pipeline, and read more details on each step below.

Drag
Installation
Process
1/12
Surveying and staking

Once the Trans Mountain pipeline route is finalized, crews survey and stake the right of way.

2/12
Right-Of-Way

The right of way is cleared of brush, and the topsoil is removed and stockpiled for future reclamation.

3/12
Digging

A trench is dug, surveyed and measured for bends.

4/12
Stringing

Individual lengths of pipe are brought in from stockpile sites and laid out end-to-end along the right of way.

5/12
Bending

Pipe is bent to horizontal and vertical curves to match right-of-way.

6/12
Joining

Welders join the pipes together using either manual or automated welding processes.

7/12
Coating

Coating is applied in the manufacturing mill, except on joint sections, which are coated in the field.

8/12
Lowering

The welded pipeline is lowered into the trench using heavy lifting machines called sidebooms.

9/12
Valves And Fittings

The valves are installed to be used once the line is operational to shut off or isolate part of the pipeline. There are generally two types of valves used.

10/12
Backfilling

Once the pipeline is in place, select backfill may be used to protect the pipe. Following this, subsoil and topsoil are replaced in the sequence in which they were removed.

11/12
Pressure Testing

The pipeline is pressure tested to 125% of its anticipated maximum operating pressure for a minimum of eight hours. A successful test is required to obtain certification for the pipeline to operate.

12/12
Cleanup

The final step is to reclaim the pipeline right-of-way, removing any temporary facilities, re-seeding and restoring the land.

Phase Value:
Last Value:
Second Last Value:
IE Counter:

Building a Pipeline

Designing and engineering a pipeline is a lengthy and detailed process. Pipeline construction consists of a number of distinct activities that each contribute to the long-term integrity of the pipeline as well as minimize the impact to the environment and to the landowner. 

Pipeline integrity begins with sourcing the materials – oil pipelines are generally constructed from steel with an inner diameter typically ranging from 100 mm to 1,200 mm (four to 48 inches). The steel used is of the highest quality and manufactured to stringent Canadian Standard Association (CSA) specifications, which include chemistry and material properties. Through production, transportation to the job site, and installation, quality management processes are in place to ensure the pipe fully meets the requirements.

Pipeline operations include multiple controls and monitoring systems to ensure it operates safely. The latest technological advancements are incorporated, along with trained personnel, to ensure that the pipeline is operated safely. With a strong focus on regular maintenance, the application of the latest technology, and sound operating practices, the Trans Mountain Pipeline has an indefinite lifespan — as safe in the future as the day it is installed.


The Pipeline Installation Process

Surveying and Staking

Once a pipeline is approved and a route is finalized, crews survey and stake the right-of-way and any temporary working space required for construction.

Right-of-Way Clearing

Trees and vegetation are removed from the right-of-way (ROW) and the topsoil is removed and stockpiled and protected for future reclamation. The crew installs silt fences along edges of streams and wetlands to prevent erosion of disturbed soil and for protection of the water courses. The ROW is then leveled and graded to provide a safe working space.

Trenching

Excavators dig the trench to the required depth and place the excavated soil to the side.

Stringing

Individual lengths of pipe ranging from 12 to 24 metres long are brought in from stockpile sites and laid out end-to-end along the right-of-way.

Bending

Individual joints of pipe are bent using a hydraulic bending machine for directional changes and to fit the terrain.

Joining

Welders join the pipes together using either manual or automated welding processes. Both manual and automatic welds are of the highest quality, with every weld inspected and certified using non-destructive examinations including X-ray or ultrasound methods.

Coating

Coating on the outside of the pipeline is used to prevent it from corrosion or rusting. The new pipe (and any repairs to the existing pipe) will typically be coated with fusion bond epoxy. In rockier areas, enhanced external coatings such as concrete, abrasive resistant fusion bond epoxy or polyethylene will be used to mitigate the impact from abrasives or stress-concentrating conditions (such as rocks or backfill) and to provide additional mechanical protection. Prior to lowering the pipe section into the trench, the integrity of the coating is checked by means of a high voltage tool that will detect even the smallest defect in the coating. If a defect is noted, an epoxy repair coating is applied.

Lowering

The welded pipeline is lowered into the trench using heavy lifting machines called sidebooms.

Valves and Fittings

Valves and other fittings are installed at intermediate locations as required by the Canadian Standards Association pipeline code. The valves are used once the line is operational to shut off or isolate part of the pipeline. There are generally two types of valves used: Check Valves and Block Valves.

  • Check Valves are mechanical devices, which only permit flow in one direction. If upstream pipeline pressure reduces, the valve closes and stops the flow.
  • Block Valves are typically automated and can be controlled remotely. They feature an electric actuator that is connected via satellite or other communications system. If a problem is detected and sent to the Control Centre as an alarm, the operator will follow written procedures, which may include stopping the pipeline and closing the Block Valves to isolate the area until the condition can be investigated and resolved.

Backfilling

Once the pipeline is in place, select backfill may be used to protect the pipe. Following this, subsoil and topsoil are replaced in the sequence in which they were removed.

Pressure Testing

The pipeline is pressure tested to 125% of its anticipated maximum operating pressure for a minimum of eight hours. This process tests the integrity of the complete system of the pipe, welds, fittings and all other appurtenances such as valves. A successful test is required to obtain certification for the pipeline to operate.

Cleanup

The final step is to reclaim the pipeline right-of-way, removing any temporary facilities, re-seeding and restoring the land.