We have many focuses from construction to safety and from environment to community dialogue and engagement.  We’ve got a wide range of topics covered here including our blog, news releases and media coverage. 

All posts

28 articles
Set Filter
Selected Tags (0) clear all
Benefits Environment Construction Emergency Management Indigenous Marine Marine Safety Pipeline Pipeline Safety Operations Regulatory Safety Expansion Project Community Investment
Type
All
Community
Spruce Grove
Blog

Project Update: Construction in Yellowhead

Construction in the Yellowhead region of Alberta includes work at pump stations, pipeline construction and trenchless crossings using horizontal directional drilling (HDD).

Blog

Project Update: Construction Progressing in Alberta

Currently, there are active sites at all phases of pipeline construction as well as work underway on a number of trenchless crossings.

Press Release

Update: COVID-19 Protocols

With the rapid developments around the COVID-19 situation, our priority continues to be the health and safety of our workforce, their families and our communities.

Blog

Backgrounder: Trans Mountain Expansion Project Construction Accelerating

The in-service date is expected to be December 2022.

Blog

Update: Construction Underway in Yellowhead

Construction activities are ramping up in Alberta, with work now underway in Yellowhead. This section of the route includes four pump stations and about 285 kilometres of pipeline construction.

Blog

Meet Backwoods Energy Services

Backwoods Energy Services is the largest Indigenous-owned business in northwestern Alberta. The company has worked with Trans Mountain since 2014 and is currently working on the Expansion Project.

Blog

Update: Work Underway Across Alberta

Construction’s underway in Alberta, including pipe transport, stringing and assembling in Greater Edmonton, right-of-way preparation in Yellowhead, work at Edmonton Terminal and two pump stations.

Press Release

Trans Mountain Marks the Start of Pipeline Construction

Expansion Project pipe is on the ground in Alberta and will be in the ground before Christmas.

Blog

Meet SA Energy Group: Construction Contractor for the Trans Mountain Expansion Project

SA Energy Group is a unionized pipeline construction contractor and an active member of the Pipeline Contractors Association of Canada.

Blog

Event Recap: Edmonton Information Session

Trans Mountain hosted an information session for our neighbours in the Edmonton area on August 27, 2019, to discuss our construction plans for the region.

1 2 3
Show 10 per page