Press Release

Trans Mountain Conducts Full-Scale Emergency Exercise in Burrard Inlet

The drill included a coordinated response with more than 300 participants/observers and 20 response agencies working collaboratively to ensure an efficient and effective response.

Blog

Update on Trans Mountain Construction Activities

Trans Mountain is winding down in-field construction activities in a safe, secure and environmentally appropriate manner.

Blog

Managing Impacts: Pile Driving at Westridge Marine Terminal Delayed While Stray Sea Lion Escorted Home to Marine Research Station

Trans Mountain delays start of impact pile driving at Westridge while stray Stellar sea lion is escorted home to marine research station at east end of Burrard Inlet.

Blog

Western Canada Marine Response Corporation Expanding to New Response Base on Lower Fraser River

A new Fraser River spill response base will be located at Shelter Island in Richmond as part of a major service expansion for the Western Canada Marine Response Corporation.

Blog

Update: Contractors for the Trans Mountain Expansion Project

Trans Mountain has selected seven contractors to lead construction of the Trans Mountain Expansion Project, which includes work on 980 kilometres of pipeline and all associated facilities.

Blog

Construction Update: Burnaby Terminal Preparatory Work Underway

At our Burnaby Terminal, preparatory work is currently underway. We are working to place a permanent double-fence system on existing Trans Mountain property.

Blog

Construction Update: Progress on Westridge Marine Terminal Expansion

​Construction has been underway for nine months at our Westridge Marine Terminal in Burnaby, as crews work to build the new three-berth dock complex

Blog

Relocation of Vapour Combustion Unit at Westridge Marine Terminal a Complex but Seamless Operation

A team of 45 people worked for 13 days to successfully relocate the Vapour Combustion Unit and associated equipment at Westridge.

Blog

The 28th Annual Great Salmon Send-Off

2018 marks the 28th year of the Great Salmon Send-Off and hundreds of people came to Stoney Creek Community School in Burnaby to celebrate.

Blog

Safe Boating Week an Opportunity for Small Vessel Operators to Focus on Safe Navigation Skills